Notice of asbestos work and ventilation shutdown
| Affected location(s): | 90 Queen's Park (017) |
| Work space(s): | First Floor Building Exterior Overhang |
| Asbestos enclosure set up: | Monday, Nov. 17, 2025, 8:00 AM |
| Asbestos enclosure removed: | Friday, Dec. 12, 2025, 5:00 PM |
Affected room(s) during ventilation shutdown period
There is no ventilation on the building exterior and no internal rooms will be affected
What is being done and why?
Contractor (Priestly Demolition) is scheduled to remove asbestos containing texture coat from the building exterior overhang ceiling as a part of the building demolition project.
What precautions are being taken?
- All asbestos activities will be performed by contractor (Priestly Demolition) following type 3 (outdoors) asbestos procedures under the supervision of a third party consultant (Safetech Environmental) to ensure compliance with all applicable Ministry of Labour and university standards.
- Access to the work areas will be restricted.
How will it impact building occupants?
- In any room listed above that does not have a fume hood, stop all activities involving airborne hazards including the use of solvents, toxic powders, CO2, liquid nitrogen, and any other toxic material that could become airborne.
- Please ensure all equipment and/or experiments are protected.
- Every effort will be made to keep the noise and disruption to a minimum. If required, any additional building system shutdowns will be kept to an absolute minimum and notice will be given to the affected building occupants.
- Any furniture required to be moved to create space for the work to occur will be moved back to the original location once the work is complete.
- No lab equipment, chemicals or any other items will be disturbed or relocated.
Who do I contact for more information?
For information on building materials containing asbestos, please visit asbestos.fs.utoronto.ca.
If you have questions or concerns about this asbestos work work, please contact Michael Somers, senior project manager, university planning, design & construction at michael.somers@utoronto.ca or 416-978-2999.
If you have questions about this ventilation shutdown, please contact Walter Mitchell, lead hand, north area at walter.mitchell@utoronto.ca or 416-684-4119.
Issued by
Doug Colby
Senior Inspector, Hazardous Construction
Irfan Miraj
Manager, Hazardous Construction Materials Group