Notice of asbestos work and ventilation shutdown
Affected location(s): | Medical Sciences Building (005) |
Work space(s): | Corridor 2138K |
Asbestos enclosure set up: | Saturday, Aug. 16, 2025, 7:00 AM |
Ventilation off: | Saturday, Aug. 16, 2025, 7:00 AM |
Ventilation on: | Saturday, Aug. 16, 2025, 3:00 PM |
Asbestos enclosure removed: | Saturday, Aug. 16, 2025, 3:00 PM |
Affected room(s) during ventilation shutdown period
2135, 2135A, 2135B, 2135C, 2135D, 2135V, 2136, 2137A, 2137C, 2137V, 2138K, 2139, 2139K, 2140A, 2140V, 2143S, 2171B, 2171C, 2171K, 2256, 2256A, 2256B, 2256C, 2256D, 2256E, 2256F, 2256G, 2256K, 2256V, 2260, 2260A, 2261, 2261A, 2262, 2263, 2267, 2354, 2354B, 2354C, 2356, 2356B, 2356C, 2356V, 2360, 2361, 2362, 2363, 2364, 2365, 2366, 2367, 2368, 2369, 2370, 2371, 2372, 2374, 2370K, 2375V, 2375, 2375A, 2375B, 3271, 3273, 3269, 3259, 3350K, 3249K, 3369K, (window radiators only 3352 A/B, 3358 A/B, 3360 A/B, 3366 A/B, 3368 D/E) 4255K, 4269, 4267, 4265, 4263, 4261, 4259, 4257, (window radiators only 4354, 4360, 4366 A/B, 4368 B/C), 5271K, 5350K, 5369K, 5272K, 5271, 5269, 5267, 5265, 5263, 5261, 5255, 5253A, 5253, (window radiators only 5354 A/B, 5360, 5366 A/B, 5368 C/D) , 6254K, 6250K, 6369K, 6374K, 6275A, 6275, 6271, 6267, 6265, 6263, 6259, 5253, (window radiators only 6352 A/B, 6356 A/B, 6360 A/B, 6368), 7271K, 7350K, 7369K, 7374K, 7271, 7267, 7265, 7263, 7259, 7255, 7255A, 7253, (window radiators only 7352A/B, 7362, 7366A/B, 7368B/C)
What is being done and why?
Ventilation will be shut down so that contractor (Quantum Murray) can inspect above the ceiling for electrical systems as a part of the ongoing EPIC project
What precautions are being taken?
- All asbestos activities will be performed by contractor (Quantum Murray) following type 2 asbestos procedures to ensure compliance with all applicable Ministry of Labour and university standards.
- Access to the work areas will be restricted.
How will it impact building occupants?
- In any room listed above that does not have a fume hood, stop all activities involving airborne hazards including the use of solvents, toxic powders, CO2, liquid nitrogen, and any other toxic material that could become airborne.
- Please ensure all equipment and/or experiments are protected.
- Every effort will be made to keep the noise and disruption to a minimum. If required, any additional building system shutdowns will be kept to an absolute minimum and notice will be given to the affected building occupants.
- Any furniture required to be moved to create space for the work to occur will be moved back to the original location once the work is complete.
- No lab equipment, chemicals or any other items will be disturbed or relocated.
Who do I contact for more information?
For information on building materials containing asbestos, please visit asbestos.fs.utoronto.ca.
If you have questions or concerns about this asbestos work work, please contact Hany Khalil, senior project manager, university planning, design & construction at hany.khalil@utoronto.ca or 437-335-0590 .
If you have questions about this ventilation shutdown, please contact Jeff Avramenko, lead hand at jeff.avramenko@utoronto.ca or 416-791-0411.
Issued by
Doug Colby
Senior Inspector, Hazardous Construction
Irfan Miraj
Manager, Hazardous Construction Materials Group