St. George campus building assessments

St. George campus building assessments

Each building on the St. George campus is audited at least once every five years to assess its age, condition and design compliance, informing planning of and budgeting for future upgrades.

Audits are completed by a specialist firm, in partnership with the property manager and building operator. This ensures that local issues and user experiences are incorporated into the audit.

From this data, we can estimate the cost of fixing a building’s deficiencies (that is, deferred maintenance) and the cost to replace a building entirely (that is, the current replacement value). These costs are then used to calculate the facility condition index for each building.

The facility condition index reflects the relative condition of buildings and allows for cross-industry comparison. It’s also part of the Facilities & Services prioritization framework for deferred maintenance work.

How to interpret the facility condition index

The lower the facility condition index, the better the assets’ condition.

Good: 0–10%

Fair: 11–20%

Poor: 21–30%

Critical: >30%

In 2024, universities across Ontario averaged a three-year facility condition index of 16.36%. The 2024 three-year facilitiy condition index for the U of T tri-campus was 16.01%.

Campus building facilities condition index values and audit dates

Building name (code)Facility condition indexAudit dateNote
Aerospace Building (049)27.70%May 2023
Anthropology Building (079)28.15%June 2023
Astronomy & Astrophysics Building (036)34.19%March 2021
Bahen Centre for Information Technology (080)5.18%August 2024
Bancroft Building (057)14.80%May 2024
Banting Institute (016)26.48%May 2023Scheduled to be demolished in 2025
371 Bloor Street West41.80%May 2023
Borden Building North (061A)19.48%April 2024
Borden Building South (061)34.43%April 2024
C. David Naylor Building (011)23.02%2025
Canadiana Gallery (047)10.33%April 2024
Clara Benson Building (068)29.57%March 2021
Claude T. Bissell Building (006A)25.93%July 2022
171 College Street (147)30.70%July 2022
179 College Street (109)13.49%July 2022
185 College Street (112)19.66%July 2022
187 College Street (114)14.00%July 2022
229 College Street (179)23.10%July 2022
88 College Street (090)25.48%June 2019
Communications House (092)2.77%2025
Convocation Hall (010A)27.43%2025
Cumberland House (026)35.87%June 2023
D.L. Pratt Building (008A)31.14%June 2022
Daniels Building (054)2.33%March 2021
Dentistry Building (065)14.12%May 2025
Dr. Eric Jackman Institute of Child Study (053)16.28%August 2022
Early Learning Centre (129)8.81%2025
Earth Sciences Centre (062)23.82%June 2022
Edward Johnson Building (051)31.54%August 2022
Electrometallurgy Lab (093)25.01%2025
Engineering Annex (021)41.62%March 2021
Enrolment Services (127)18.02%August 2022
Exam Centre (155)0.36%June 2023
Factor-Inwentash Faculty of Social Work (111)22.42%2025
Faculty of Law (040)4.44%May 2024
Falconer Hall (050)27.44%April 2024
Fasken Martineau Building (151)15.42%April 2024
Fields Institute for Research in Math Science (105)34.03%2025
FitzGerald Building (025)40.46%2025FCI prior to retrofit
Gage Building (082)26.81%April 2024
Galbraith Building (070)29.25%June 2023
Gerstein Science Information Centre in the Sigmund Samuel Library Bldg (003)20.62%2025
Goldring Centre for High Performance Sport (042)0.08%May 2024
Graduate Students’ Union (056)28.20%April 2024
Gull Lake – Dining Hall (901C)26.26%April 2023
Gull Lake – Men’s Bunkhouse (901B)16.70%April 2023
Gull Lake – Men’s Bunkhouse washroom (901I)4.85%April 2023
Gull Lake – Pump House (901F)3.92%April 2023
Gull Lake – Skulehouse (classrooms) (901A)19.24%April 2023
Gull Lake – Staff House (901E)10.76%April 2023
Gull Lake – Stewart Hall (901D)18.38%April 2023
Gull Lake – Water Tower (Gull Lake) (901K)121.02%April 2023
Haultain Building (024)26.87%May 2023
Health Sciences Building (154)16.09%June 2023
215 Huron Street (067)25.14%April 2024
370 Huron Street (138)6.83%April 2024
Innis College (132)23.27%2019Expansion underway
J. Robert S. Prichard Alumni House (019)18.34%2025
Jackman Humanities Building (128)31.80%March 2021
John P. Robarts Library Building (006)26.74%July 2022
Knox College (575)35.92%April 2022
Koffler House (145)18.53%2025
Koffler Student Services Centre (143)31.97%April 2024
Lash Miller Chemical Laboratories (073)15.86%June 2018Expansion underway
Lassonde Mining Building (007)23.76%March 2021
Leslie L. Dan Pharmacy Building (161)6.59%July 2022
Louis B. Stewart Observatory (UTSU) (120)29.77%2025
Luella Massey Studio Theatre (091)39.65%April 2024
Macdonald-Mowat House (172)10.36%April 2022
Massey College (034)30.58%2025
Max Gluskin House (104)13.19%August 2022
254-256 McCaul Street (083)28.11%May 2023
263 McCaul Street (156)20.89%June 2023
McLennan Physical Laboratories (078)44.68%June 2023
McMurrich Building (004)25.76%May 2023
Mechanical Engineering Building (022)17.24%2025
Medical Sciences Building (005)33.67%2025
Munk School of Global Affairs & Public Policy at the Observatory (089)5.12%August 2022
Munk School of Global Affairs & Public Policy at Trinity (012A)2025
Myhal Centre for Engineering Innovation & Entrepreneurship (087)0.39%May 2024
Ontario Institute for Studies in Education (OISE) (123)22.27%May 2024
93 Highland Avenue (055)35.76%November 2020
39 Queen’s Park Crescent East (097)28.13%May 2020
39A Queen’s Park Crescent East (097A)28.45%May 2020
Ramsay Wright Laboratories (072)24.51%May 2023
Rehabilitation Sciences Building (152)5.16%July 2022
Rosebrugh Building (020)42.27%May 2023
Rotman School of Management (134)3.31%May 2023
Sandford Fleming Building (009)31.37%March 2021
School of Continuing Studies (103)3.77%2025
School of Graduate Studies (043)26.38%2025
Sidney Smith Hall (033)34.47%March 2021
Simcoe Hall (010)14.08%June 2023
Soldiers’ Tower (102)1.48%2025
665 Spadina Avenue (066)36.85%April 2024
703 Spadina Avenue (125)31.93%2025
121 St. George Street (110)20.60%April 2024
123 St. George Street (088)19.49%May 2024
162 St. George Street (106)37.58%May 2023
45 St. George Street 31.71%2025
Student Commons (028)16.83%August 2022FCI prior to renovation
40 Sussex Avenue (146)21.69%April 2024
Sussex Court (077)40.31%2025
Terrence Donnelly Centre for Cellular & Biomolecular Research (160)6.64%June 2022
Thomas Fisher Rare Book Library (006B)37.53%July 2022
University College (001)25.44%2025
University College Union (023)19.66%June 2023
UTL at Downsview (149)0.20%May 2023
Wallberg Building (008)20.80%March 2021
Warren Stevens Building (068A)34.51%March 2021
90 Wellesley Street West (098B)25.42%2025
90 Wellesley Street West (098C)34.92%2025
Wetmore Hall – New College (032)25.13%2025
Wilson Hall – New College (032A)22.48%2025
Woodsworth College (038)19.53%May 2024