Pomerleau Construction is excavating and installing/hoisting a new concrete valve chamber, which requires closing St George Street, boulevards, sidewalks, and roads as per the permits and traffic plans linked below. This work is part of the P108-14-088: Academic Wood Tower project.

1. May 5 to May 6- 6 AM to 6 PM Sidewalk closure to allow for truck parking and hydro excavation

123 ST GEORGE ST – 1014139001123 ST GEORGE ST

123 ST GEORGE ST – 1014466001 – Occupancy Plan for Chamber Area Preparation

2. May 7 to May 9-6 AM to 6 PM Sidewalk and Boulevard Closure to complete excavation activities

123 ST GEORGE ST – 1014466001

123 ST GEORGE ST – 1014466001 – Occupancy Plan for Chamber Excavation

3.May 10 to May 11-7 AM to 5 PM daily Road Closure for hoisting of valve chamber

123 ST GEORGE ST – 1014470001

123 ST GEORGE ST – 1014470001 – Closure Plan for Chamber Install

 

How will it impact building occupants?

  • Pomerleau Construction will have personnel on site.
  • Access to the affected area will be limited or restricted.
  • Traffic control and a flag person will be on site to direct traffic as needed. ยท Rerouting signage will be available.
  • View the Road closure plans in the links above for more information.
  • Accessible parking will remain available.

Who do I contact for more information?

Adam Kozak, 437-860-8729, a.kozak@utoronto.ca

If you have questions or concerns, please contact Paul Gargaro, construction technician, university planning, design & construction at paul.gargaro@utoronto.ca or 416-500-6920.


Issued by

Paul Gargaro
Construction Technician, University Planning, Design & Construction